New Hospital Timeline

  • WMMS announced in January 2004 its intention to move to a single-campus hospital, either at one of the existing hospitals or at a new facility
  • WMHS Board approved plan to build new hospital on Willowbrook Road in September 2004
  • Over 300 physicians and employees participated in Design Development phase beginning in late Fall 2004
  • CON applied for in August 2005 and approved in March 2006 by Maryland Health Care Commission (MHCC)
    • 275-bed 585,000 square feet replacement hospital
    • Estimated total cost $359 million
      • $228 in construction
      • Plus equipment, A & E, interest during construction, debt service reserve, financing cost, refinance existing debt, etc.
  • Acquired the former M & T Call Center for administrative space
  • Purchased Kelly-Springfield Tire Company's former offices and tire testing center
  • Partnered with Allegany County to renovate buildings for new home for Allegany County Health Department
  • Exchanged property with Allegany County to gain ownership of new hospital site
  • Barton Malow/Mascaro retained as Construction Manager
  • Full architectural plans completed by Hord Coplan Macht in Spring 2006
  • Price for construction materials started to rise dramatically
  • Guaranteed maximum price received in Sept 2006 was $40 million over original estimates
  • CON modified and approved by MHCC in Sept 2006
  • New approved amount is $406 million
    • $268 in construction costs
    • Slight increase in related costs
  • Bonds issued by Maryland Health and Higher Education Financing Authority
    • Security for Bonds - Mortgage and Bond Insurance\
    • Mortgage secured by HUD FHA 242 Program
  • Groundbreaking for new hospital on October 25, 2006
  • Completion Date: Fall 2009